| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| HER-05 | SUMINISTRO Y COLOCACION DE FALDON DE ESTRUCTURA METALICA A BASE DE TUBULAR PTR REFORZADO DE 4", CON ARMADO DE ESTRUCTURA TIPO CRUCETA. ESPECIFICADO EN PROYECTO. INCLUYE: MATERIAL, MANO DE OBRA, HERRAMIENTA, EQUIPO, ACARREOS, ELEVACIONES, Y TODO LO NECESARIO PARA SU CORRECTA COLOCACION. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PERFIL DE ACERO | PERFIL DE ACERO | KG | 18.000000 | $10.00 | $180.00 |
| LAMINA ZINTRO | LAMINA CALIBRE 22 | M2 | 1.100000 | $80.00 | $88.00 |
| PIJA2X10 | PIJA 2 X 10 | pza | 4.000000 | $0.75 | $3.00 |
| PINTURA PRIMARIO | PINTURA PRIMARIO | LT | 0.020000 | $45.00 | $0.90 |
| PINTURA-03 | PINTURA DE ESMALTE COMEX 100 | LT | 0.100000 | $65.00 | $6.50 |
| PINTURA-06 | THINNER | LT. | 0.010000 | $16.50 | $0.17 |
| GAS LP | GAS | LT | 0.020000 | $5.00 | $0.10 |
| OXIGENO | OXIGENO | M3 | 0.050000 | $38.00 | $1.90 |
| SOLDADURA 7018 | SOLDADURA 70/18 | KG | 0.100000 | $29.00 | $2.90 |
| Suma de Material | $283.47 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.050000 | $972.90 | $48.65 |
| CUADRILLA NO. 42 | (1 Pailero + 1 Soldador + 2 ayudantes A). | Jor | 0.100000 | $790.01 | $79.00 |
| CUADRILLA NO. 18 | (1 Of. Pintor +2 Ayudante). | Jor | 0.005263 | $540.83 | $2.85 |
| Suma de Mano de Obra | $130.49 | ||||
| Herramienta | |||||
| ANDAMIO METALICO | (%)mo | 0.040000 | $0.00 | $0.00 | |
| Suma de Herramienta | $0.00 | ||||
| Costo Directo | $413.96 |