| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| ALB-11 | HECHURA DE CISTERNA EN AREA DE FARMACIA DE 5,000 M3 DE CAP. INCLUYE; EXCAVACION A MANO, RETIRO DE MATERIAL PRODUCTO DE EXCAVACION, ACARREOS, ARMADO DE CISTERNA CON VAR 3/8 " A CADA 15 CMS EN AMBOS SENTIDOS, CASTILLOS DE 15 X 20 ARMADOS CON VAR. DE 3/8 " EST. 1/4 " A CADA 15 CMS, CADENA DE 15 X 20 CON VAR. 3/8" EST. 1/4" A CADA 15 CMS Y LOSA DE CONCRETO ARMADO CON VAR. 3/8" EST. 1/4" A CADA 15 CMS. A.S. TODO CON CONCRETO F'C= 200 KG/CM2, APLANADO FINO PULIDO EN MUROS, CARCAMO, PREPARACION PAR TAPA EN CISTERNA, MATERIAL Y MANO DE OBRA. | LOTE |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TABIQUE ROJO REC | PZA | 650.000000 | $1.00 | $650.00 | |
| CIMBRA 04 | MADERA PINO 3a. | PT | 11.000000 | $7.00 | $77.00 |
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 2.000000 | $84.00 | $168.00 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 1.500000 | $10.00 | $15.00 |
| ACERO-021 | ALAMBRE RECOCIDO | KG | 3.000000 | $10.00 | $30.00 |
| MARCO MET, P/REG. | DE 40 X 60 CM. | PZA | 1.000000 | $190.00 | $190.00 |
| ACERO 03 | ACERO DEL # 3 AL 6 | KG | 244.000000 | $7.40 | $1,805.60 |
| MORTERO CEM-ARE. 1:4 | Mortero cemento arena 1:4 | M3 | 0.640000 | $643.32 | $411.72 |
| CONCRETO F-C=200 H/O | Concreto f'c=200 kg/cm2 hecho en obra resistencia normal, agregado maximo 3/4" | M3 | 2.600000 | $747.81 | $1,944.31 |
| Suma de Material | $5,291.63 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 01 | (1 pe贸n). | Jor | 4.000000 | $157.11 | $628.44 |
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Pe贸n) | Jor | 7.000000 | $386.01 | $2,702.07 |
| Suma de Mano de Obra | $3,330.51 | ||||
| Costo Directo | $8,622.14 |