| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | | | | |
| 550100-1005 | Cisterna 1000 Lts azul | pza | 1.000000 | $2,884.10 | $2,884.10 |
| Suma de Material | | | | $2,884.10 |
| Concepto | | | | |
| FDA-CIM_INT-002 | EXCAVACION EN CAJA MEDIDO EN BANCO EN MATERIALES TIPO 1 Y 2 POR MEDIOS MANUALES. Y RETIRO DE MATERIAL SOBRANTE FUERA DE LA OBRA. PARA ALOJAR CIMENTACIÓN INCLUYE: MANO DE OBRA, HERRAMIENTA, EQUIPO, CARGA, DESCARGA, FLETE. | M3 | 4.000000 | $74.10 | $296.40 |
| FDA-ALB_INT-003 | FIRME DE CONCRETO F'C= 200KG/CM2 HECHO EN OBRA CON TROMPO T.M.A. 3/4" DE 10 CM. DE ESPESOR EN AREA DE TRASBOTICA, ARMADO CON MALLA ELECTROSOLDADA 6x6/10-10, Fy= 4,200 KG/CM2, ACABADO PULIDO INTEGRAL. INCLUYE: :HABILITADO, ARMADO, CIMBRADO, VACIADO, VIBRADO POR MEDIOS MECANICOS, DESCIMBRADO, CURADO, CORTES CON DISCO PARA HACER JUNTAS DE CONTROL EN CUADROS DE 2.50 X 2.50 M, MATERIAL, MANO DE OBRA, HERRAMIENTA Y EQUIPO. | M2 | 2.250000 | $241.21 | $542.72 |
| FDA-ALB_INT-005 | MURO A BASE DE BLOCK HUECO DE CONCRETO 15x20x40 CM. CURADO A VAPOR, RESISTENCIA MINIMA DE 40 KG/CM2, ASENTADO CON MORTERO CEMENTO-ARENA 1:4, CON REFUERZO DE VARS No. 3 @ 0.80 M. Y ESCALERILLA @ 3 HILADAS. INCLUYE: CASTILLOS AHOGADOS @ 0.80 M, MATERIALES, MANO DE OBRA, HERRAMIENTA Y EQUIPO. | M2 | 9.000000 | $161.50 | $1,453.50 |
| FDA-ALB_INT-015 | IMPERMEABILIZACION EN CIMENTACIÓN Y DESPLANTE DE MUROS A BASE DE PROTECTOR HIDROPRIMER (IMPRIMIDOR ASFALTICO TAPA PORO BASE SOLVENTE) ADICIONALMENTE BARRERA DE VAPOR (IMPERMEABILIZANTE ASFALTICO BASE SOLVENTE RESISITENTE AL AGU Y HUMEDASD PERMANENTE ) MARCA FIRESTON, PASA,IMPERQUIMIA, TEXSA O FESTER, MODELO HIDROPIMER BARRERA DE VAPOR. INCLUYE: DESPERDICIO, MATERIALES, MANO DE OBRA, HERAMIENTA Y EQUIPO. | M2 | 9.000000 | $137.82 | $1,240.38 |
| FDA-ALB_INT-008 | CASTILLOS K-1 DE CONCRETO F'C=250 KG/CM2 T.M.A. 3/4" HECHO EN OBRA CON TROMPO, 15x15 CM. ARMADO CON 4 VRS. No. 3 (3/8") Y ESTRIBOS No. 2 (1/4") @ 15 CM. INCLUYE: HABILITADO, ARMADO, CIMBRADO, VACIADO, VIBRADO POR MEDIOS MECANICOS, DESCIMBRADO, CURADO, DESPERDICIOS, APLICACION | ML | 6.000000 | $188.67 | $1,132.02 |
| FDA-EST_INT-004 | DALA DE CERRAMIENTO T-3 15X20 CMS. DE CONCRETO ARMADO F'C= 200 KGS/CM2, ARMADO CON 4 VARS. No. 3 Y ESTRIBOS No. 3 @15 CMS FY=4200 KG/CM2, CONCRETO HECHO EN OBRA CON TROMPO. INCLUYE: HABILITADO, ARMADO, CIMBRADO, VACIADO, VIBRADO POR MEDIOS MECANICOS, DESCIMBRADO, CURADO, DESPERDICIOS, MATERIALES, MANO DE OBRA, HERRAMIENTA, Y EQUIPO. | ML | 6.000000 | $423.59 | $2,541.54 |
| FDA-CIM_EXT-006 | RELLENO EN CIMENTACIÓN CON MATERIAL PRODUCTO DE EXCAVACIÓN COMPACTADO POR MEDIOS MECANICOS AL 95% PROCTOR MODIFICADO EN CAPAS PROMEDIO DE 20 CMS. PARA DAR NIVEL REQUERIDO. INCLUYE: MATERIALES, MANO DE OBRA, HERRAMIENTA, EQUIPO, Y NIVELACION. | M3 | 1.500000 | $77.11 | $115.67 |
| G115130-1000 | Losa plana en super estructura de 10 cm. de peralte, fabricada con concreto fc=200 kg/cm2, r.n. agreg.max. 20 mm. (3/4"), incluye: cimbra acabado comun, descimbra, habilitado de 70 kg de acero de refuerzo de 5/8" y 1/2" x m3. de concreto, materiales, ma | m2 | 2.250000 | $390.29 | $878.15 |
| Suma de Concepto | | | | $8,200.38 |
| Costo Directo | | | | $11,084.48 |