| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIM-06 | FABRICACIÓN DE DADOS DE CONCRETO F´c=250 KG/CM2, REVENIMIENTO DE 10-12 CMS, AGREGADO MÁXIMO DE 3/4", DE 45x45x80CMS. ARMADOS CON 8 VARS.#5, ESTRIBOS DEL #3 @ 15 CMS. INC.: MATERIAL, MANO DE OBRA, HERRAMIENTA, EQUIPO, ACARREO, CIMBRA, COLADO, VIBRADO, DESCIMBRADO. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO F-C=250 H/O | Concreto F'c=250 Kg/cm2 RN rev 10 cmAM 3/4" | M3 | 0.200000 | $868.90 | $173.78 |
| ACERO 03 | ACERO DEL # 3 AL 6 | KG | 13.970000 | $7.40 | $103.38 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 1.200000 | $7.00 | $8.40 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.100000 | $10.00 | $1.00 |
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.300000 | $84.00 | $25.20 |
| CONCRETO 04 | DESMOLDANTE SEPAROL DE SIKA | LT | 0.500000 | $10.00 | $5.00 |
| ACERO-021 | ALAMBRE RECOCIDO | KG | 0.010000 | $10.00 | $0.10 |
| Suma de Material | $316.86 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | Jor | 0.500000 | $386.01 | $193.01 |
| CUADRILLA NO. 01 | (1 peón). | Jor | 0.100000 | $157.11 | $15.71 |
| Suma de Mano de Obra | $208.72 | ||||
| Equipo | |||||
| VIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | HR | 0.100000 | $15.40 | $1.54 |
| Suma de Equipo | $1.54 | ||||
| Costo Directo | $527.11 |