| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 3 | EFECTUAR REVISICION Y REAPRIETE DE CONEXIONES INTERNAS | SERVICIO |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| SOL1 | SOLVENTE DIELECTRICO SS-25 | LTS | 2.000000 | $140.00 | $280.00 |
| C005SGP | BROCHA DE 2" DE ANCHO, MARCA PERFECT | PIEZA | 2.000000 | $24.50 | $49.00 |
| CINT | CINTURONES DE PLASTICO | PIEZA | 10.000000 | $7.00 | $70.00 |
| C-001-CDS | TRAPO DE PRIMERA | KG | 7.000000 | $20.51 | $143.57 |
| GRASA.1 | GRASA ANTIFERRANTE | KGS | 1.000000 | $506.76 | $506.76 |
| Suma de Material | $1,049.33 | ||||
| Mano de Obra | |||||
| CUAD-08 | CUADRILLA DE ELECTRICISTA | JOR | 4.000000 | $1,897.81 | $7,591.24 |
| CUA23 | CUADRILLA 2 MANIOBRISTAS | JOR | 2.000000 | $995.95 | $1,991.90 |
| Suma de Mano de Obra | $9,583.14 | ||||
| Herramienta | |||||
| %MO01 | HERRAMIENTA MENOR | (%)MO | 0.050000 | $0.00 | $0.00 |
| %MO02 | EQUIPO DE SEGURIDAD | (%)MO | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| EQUI | EQUIPO HIDRAULICO DE TORQUE | hora | 12.000000 | $12.30 | $147.60 |
| Suma de Equipo | $147.60 | ||||
| Costo Directo | $10,780.07 |