| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| EST.14 | CONCRETO F'C=250 KG/CM2 EN LOSA DE FONDO Y MUROS | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCR04. | CONCRETO PREMEZCLADO F'C=250 10-13 | M3 | 1.050000 | $1,045.00 | $1,097.25 |
| IMPERMINTEGRAL | IMPERMEABILIZANTE INTEGRAL INCLUIDO EN EL CONCRETO. | M3 | 1.050000 | $80.00 | $84.00 |
| BOMBA/CONCRETO | BOMBA PARA CONCRETO | M3 | 1.050000 | $130.00 | $136.50 |
| CURACRETO | CURACRETO | LT | 0.400000 | $18.85 | $7.54 |
| AGUA | AGUA | m3 | 0.040000 | $5.00 | $0.20 |
| Suma de Material | $1,325.49 | ||||
| Mano de Obra | |||||
| CUAD OC 42 | 1 Of: Albañil + 2 Ayud.) | jor | 0.120000 | $1,034.65 | $124.16 |
| O.CIVIL-09 | AYUDANTE DE OFICIAL | Jor | 0.080000 | $278.24 | $22.26 |
| Suma de Mano de Obra | $146.42 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR. | HERRAMIENTA MENOR | (%)mo | 0.020000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| C.F. VIBRADOR CONCRE | VIBRADOR | HR | 0.791000 | $11.90 | $9.41 |
| Suma de Equipo | $9.41 | ||||
| Costo Directo | $1,481.32 |