| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| OPC.03 | PISO DE CONCRETO DE 15 CM. DE ESPESOR REF. CON DOBLE MALLA 6X6-6/6. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONC.PREMEZ.F-C=250 | Concreto Premezclado F'c=250 Kg/cm2 T.M.A. 3/4" revenimiento tiro directo | M3 | 0.160000 | $965.00 | $154.40 |
| MALLA 66/100 | MALLA ELECTROSOLDADA 6/6 10-10 | M2 | 2.200000 | $24.00 | $52.80 |
| ALAMBREREC18 | ALAMBRE RECOCIDO No. 18 | Kg | 0.010000 | $14.00 | $0.14 |
| ACERO VARIOS D | ACERO DE REFUERZO DE DIFERENTES DIAMETROS | KG | 0.200000 | $9.50 | $1.90 |
| CIMBRAMETALICA | CIMBRA METALICA(CANAL MONTEN) | ML | 0.014300 | $80.10 | $1.15 |
| AGUA | AGUA | m3 | 0.021000 | $5.00 | $0.11 |
| Suma de Material | $210.49 | ||||
| Mano de Obra | |||||
| CUAD OC 05 | (1 Of. Albañil + 5 Peones) | jor | 0.023000 | $1,911.11 | $43.96 |
| CUAD OC 62 | (1 Of. Fierrero + 1 Ayud.) | jor | 0.010000 | $742.50 | $7.43 |
| Suma de Mano de Obra | $51.38 | ||||
| Equipo | |||||
| REGLA VIBRATORIA | REGLA VIBRATORIA | hora | 0.003571 | $209.63 | $0.75 |
| ALLANADORA MECANIC. | ALLANADORA MECANICA CON ASPAS | hora | 0.015000 | $58.01 | $0.87 |
| Suma de Equipo | $1.62 | ||||
| Costo Directo | $263.49 |