| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| I.2 | SUMINISTRO, HABILITADO Y FABRICACION DE ESTRUCTURA METALICA LIGERA A BASE DE PERFILES LAMINADOS Y ARMADOS CON PLACA A-36 (ESCALERAS, BARANDALES, PUERTAS); INCLUYE: MATERIALES, DESPERDICIOS, MANO DE OBRA, TORNILLERIA, HERRAMIENTA Y EQUIPO. LIMPIEZA MECANICA SSPC-SP10 SEGUN ESPECIFICACION, APLICACION DE PRIMARIO INORGANICO DE ZINC A 3 MILS DE PULGADA DE ESPESOR Y ACABADO AMERCOAT 385 A 5 MILS DE PULGADA DE ESPESOR. | KG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| IPR DIF. MEDIDAS | KG | 0.379750 | $11.70 | $4.44 | |
| PLACA 1/4"@ 1" | KG | 0.542500 | $9.90 | $5.37 | |
| CANAL ESTRUCTURAL | KG | 0.108500 | $9.90 | $1.07 | |
| ANGULO DIF. MEDIDAS | KG | 0.054250 | $9.90 | $0.54 | |
| GAS P/ CORTES | KG | 0.009000 | $5.05 | $0.05 | |
| OXIGENO | M3 | 0.013000 | $15.00 | $0.20 | |
| SOLDADURA E7018 | SOLDADURA E 7018 | KG | 0.011000 | $32.00 | $0.35 |
| ALAMBRE TUBULAR | KG | 0.010000 | $46.00 | $0.46 | |
| DISCO ABRASIVO | PZA | 0.002200 | $41.00 | $0.09 | |
| TORNILLERIA | KG | 0.003600 | $50.00 | $0.18 | |
| FLETES Y MANEJOS | (%)m | 0.007849 | $0.00 | $0.00 | |
| Suma de Material | $12.75 | ||||
| Mano de Obra | |||||
| CUADRILLA N° 341 | 1 of.pailero + 1 ayudante E. | JOR | 0.005264 | $569.96 | $3.00 |
| CUADRILLA N° 342 | 1 of.soldador + 1 ayudante E. | JOR | 0.004390 | $569.96 | $2.50 |
| Suma de Mano de Obra | $5.50 | ||||
| Equipo | |||||
| EQUIPO DE CORTE | Equipo de corte de oxi-acetileno | HR | 0.013880 | $6.05 | $0.08 |
| ESMERILADORA | Esmeriladora | HR | 0.028440 | $2.11 | $0.06 |
| SOLDADORA | Soldadora Miller Mod. S64 | HR | 0.011440 | $8.74 | $0.10 |
| GRUA | Grua de 20 ton. | HR | 0.001227 | $371.86 | $0.46 |
| Suma de Equipo | $0.70 | ||||
| Auxiliar | |||||
| SAND BLAST | Limpieza mecanica (sand blast) | M2 | 0.030000 | $53.78 | $1.61 |
| SISTEMA 2 | M2 | 0.029900 | $84.00 | $2.51 | |
| Suma de Auxiliar | $4.13 | ||||
| Costo Directo | $23.08 |