| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| I.I.1 | SUMINISTRO, HABILITADO, FABRICACION Y MONTAJE DE PLACA DE ANCLAJE A BASE DE PLACA A -36 DE 3/4" Y REDONDO DE 3/4" DE DIAMETRO; INCLUYE: MATERIALES, DESPERDICIOS, MANO DE OBRA, HERRAMIENTA Y EQUIPO. | KG |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PLACA A-36 | KG | 1.085000 | $12.70 | $13.78 | |
| GAS P/ CORTES | KG | 0.009000 | $8.70 | $0.08 | |
| OXIGENO | M3 | 0.013000 | $19.00 | $0.25 | |
| SOLDADURA E7018 | SOLDADURA E 7018 | KG | 0.020000 | $45.00 | $0.90 |
| DISCO ABRASIVO | PZA | 0.002200 | $45.00 | $0.10 | |
| FLETES Y MANEJOS | (%)m | 0.006969 | $0.00 | $0.00 | |
| Suma de Material | $15.10 | ||||
| Mano de Obra | |||||
| CUADRILLA N掳 341 | 1 of.pailero + 1 ayudante E. | JOR | 0.003430 | $583.02 | $2.00 |
| CUADRILLA N掳 342 | 1 of.soldador + 1 ayudante E. | JOR | 0.002573 | $583.02 | $1.50 |
| CUADRILLA N掳 343 | 1 of.montador + 4 ayudante A. | JOR | 0.002873 | $1,044.32 | $3.00 |
| Suma de Mano de Obra | $6.50 | ||||
| Equipo | |||||
| EQUIPO DE CORTE | Equipo de corte de oxi-butano | HR | 0.013880 | $9.56 | $0.13 |
| ESMERILADORA | Esmeriladora | HR | 0.028440 | $2.88 | $0.08 |
| SOLDADORA | Soldadora Miller Mod. S64 | HR | 0.011440 | $12.48 | $0.14 |
| GRUA 30 TON | Grua de 20 ton. | HR | 0.002204 | $371.86 | $0.82 |
| Suma de Equipo | $1.18 | ||||
| Costo Directo | $22.78 |