| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | | | | |
| E-AGLUTINANTES | CALHIDRA EN SACO | ton | 0.000200 | $1,200.00 | $0.24 |
| E-AGLUTINANTES | CALHIDRA EN SACO | ton | 0.000200 | $1,200.00 | $0.24 |
| E-AGLUTINANTES | CALHIDRA EN SACO | ton | 0.000200 | $1,200.00 | $0.24 |
| E-AGLUTINANTES | CALHIDRA EN SACO | ton | 0.000200 | $1,200.00 | $0.24 |
| E-AGLUTINANTES | CALHIDRA EN SACO | ton | 0.000200 | $1,200.00 | $0.24 |
| E-AGLUTINANTES | CALHIDRA EN SACO | ton | 0.000200 | $1,200.00 | $0.24 |
| E-AGLUTINANTES | CALHIDRA EN SACO | ton | 0.000200 | $1,200.00 | $0.24 |
| E-AGLUTINANTES | CALHIDRA EN SACO | ton | 0.000200 | $1,200.00 | $0.24 |
| E-AGLUTINANTES | CALHIDRA EN SACO | ton | 0.000200 | $1,200.00 | $0.24 |
| E-AGLUTINANTES | CALHIDRA EN SACO | ton | 0.000200 | $1,200.00 | $0.24 |
| E-CIMBRA -ESTACAS | Madera para estacas | pt | 0.150000 | $4.34 | $0.65 |
| E-CIMBRA -ESTACAS | Madera para estacas | pt | 0.150000 | $4.34 | $0.65 |
| E-CIMBRA -ESTACAS | Madera para estacas | pt | 0.150000 | $4.34 | $0.65 |
| E-CIMBRA -ESTACAS | Madera para estacas | pt | 0.150000 | $4.34 | $0.65 |
| E-CIMBRA -ESTACAS | Madera para estacas | pt | 0.150000 | $4.34 | $0.65 |
| E-CIMBRA -ESTACAS | Madera para estacas | pt | 0.150000 | $4.34 | $0.65 |
| E-CIMBRA -ESTACAS | Madera para estacas | pt | 0.150000 | $4.34 | $0.65 |
| E-CIMBRA -ESTACAS | Madera para estacas | pt | 0.150000 | $4.34 | $0.65 |
| E-CIMBRA -ESTACAS | Madera para estacas | pt | 0.150000 | $4.34 | $0.65 |
| E-CIMBRA -ESTACAS | Madera para estacas | pt | 0.150000 | $4.34 | $0.65 |
| E-PINTURA ESMALTE 10 | PINTURA ESMALTE ALQUIDALICO COMEX 100 | litro | 0.003500 | $66.56 | $0.23 |
| E-PINTURA ESMALTE 10 | PINTURA ESMALTE ALQUIDALICO COMEX 100 | litro | 0.003500 | $66.56 | $0.23 |
| E-PINTURA ESMALTE 10 | PINTURA ESMALTE ALQUIDALICO COMEX 100 | litro | 0.003500 | $66.56 | $0.23 |
| E-PINTURA ESMALTE 10 | PINTURA ESMALTE ALQUIDALICO COMEX 100 | litro | 0.003500 | $66.56 | $0.23 |
| E-PINTURA ESMALTE 10 | PINTURA ESMALTE ALQUIDALICO COMEX 100 | litro | 0.003500 | $66.56 | $0.23 |
| E-PINTURA ESMALTE 10 | PINTURA ESMALTE ALQUIDALICO COMEX 100 | litro | 0.003500 | $66.56 | $0.23 |
| E-PINTURA ESMALTE 10 | PINTURA ESMALTE ALQUIDALICO COMEX 100 | litro | 0.003500 | $66.56 | $0.23 |
| E-PINTURA ESMALTE 10 | PINTURA ESMALTE ALQUIDALICO COMEX 100 | litro | 0.003500 | $66.56 | $0.23 |
| E-PINTURA ESMALTE 10 | PINTURA ESMALTE ALQUIDALICO COMEX 100 | litro | 0.003500 | $66.56 | $0.23 |
| E-PINTURA ESMALTE 10 | PINTURA ESMALTE ALQUIDALICO COMEX 100 | litro | 0.003500 | $66.56 | $0.23 |
| Suma de Material | | | | $11.24 |
| Mano de Obra | | | | |
| CUAD OC 10 | CUAD. 1 TOPOGRAFO + 2 CADENEROS
| jor | 0.004000 | $1,378.22 | $5.51 |
| CUAD OC 10 | CUAD. 1 TOPOGRAFO + 2 CADENEROS
| jor | 0.004000 | $1,378.22 | $5.51 |
| CUAD OC 10 | CUAD. 1 TOPOGRAFO + 2 CADENEROS
| jor | 0.004000 | $1,378.22 | $5.51 |
| CUAD OC 10 | CUAD. 1 TOPOGRAFO + 2 CADENEROS
| jor | 0.004000 | $1,378.22 | $5.51 |
| CUAD OC 10 | CUAD. 1 TOPOGRAFO + 2 CADENEROS
| jor | 0.004000 | $1,378.22 | $5.51 |
| CUAD OC 10 | CUAD. 1 TOPOGRAFO + 2 CADENEROS
| jor | 0.004000 | $1,378.22 | $5.51 |
| CUAD OC 10 | CUAD. 1 TOPOGRAFO + 2 CADENEROS
| jor | 0.004000 | $1,378.22 | $5.51 |
| CUAD OC 10 | CUAD. 1 TOPOGRAFO + 2 CADENEROS
| jor | 0.004000 | $1,378.22 | $5.51 |
| CUAD OC 10 | CUAD. 1 TOPOGRAFO + 2 CADENEROS
| jor | 0.004000 | $1,378.22 | $5.51 |
| CUAD OC 10 | CUAD. 1 TOPOGRAFO + 2 CADENEROS
| jor | 0.004000 | $1,378.22 | $5.51 |
| Suma de Mano de Obra | | | | $55.13 |
| Equipo | | | | |
| 03-0040 | ESTACION TOTAL | hr | 0.009091 | $60.81 | $0.55 |
| 03-0040 | ESTACION TOTAL | hr | 0.009091 | $60.81 | $0.55 |
| 03-0040 | ESTACION TOTAL | hr | 0.009091 | $60.81 | $0.55 |
| 03-0040 | ESTACION TOTAL | hr | 0.009091 | $60.81 | $0.55 |
| 03-0040 | ESTACION TOTAL | hr | 0.009091 | $60.81 | $0.55 |
| 03-0040 | ESTACION TOTAL | hr | 0.009091 | $60.81 | $0.55 |
| 03-0040 | ESTACION TOTAL | hr | 0.009091 | $60.81 | $0.55 |
| 03-0040 | ESTACION TOTAL | hr | 0.009091 | $60.81 | $0.55 |
| 03-0040 | ESTACION TOTAL | hr | 0.009091 | $60.81 | $0.55 |
| 03-0040 | ESTACION TOTAL | hr | 0.009091 | $60.81 | $0.55 |
| Suma de Equipo | | | | $5.53 |
| Auxiliar | | | | |
| AUX-09 | CONCRETO HECHO EN OBRA F'c = 100 KG/CM2 AGREGADO MAX. 3/4" R.N. | m3 | 0.000700 | $865.29 | $0.61 |
| AUX-09 | CONCRETO HECHO EN OBRA F'c = 100 KG/CM2 AGREGADO MAX. 3/4" R.N. | m3 | 0.000700 | $865.29 | $0.61 |
| AUX-09 | CONCRETO HECHO EN OBRA F'c = 100 KG/CM2 AGREGADO MAX. 3/4" R.N. | m3 | 0.000700 | $865.29 | $0.61 |
| AUX-09 | CONCRETO HECHO EN OBRA F'c = 100 KG/CM2 AGREGADO MAX. 3/4" R.N. | m3 | 0.000700 | $865.29 | $0.61 |
| AUX-09 | CONCRETO HECHO EN OBRA F'c = 100 KG/CM2 AGREGADO MAX. 3/4" R.N. | m3 | 0.000700 | $865.29 | $0.61 |
| AUX-09 | CONCRETO HECHO EN OBRA F'c = 100 KG/CM2 AGREGADO MAX. 3/4" R.N. | m3 | 0.000700 | $865.29 | $0.61 |
| AUX-09 | CONCRETO HECHO EN OBRA F'c = 100 KG/CM2 AGREGADO MAX. 3/4" R.N. | m3 | 0.000700 | $865.29 | $0.61 |
| AUX-09 | CONCRETO HECHO EN OBRA F'c = 100 KG/CM2 AGREGADO MAX. 3/4" R.N. | m3 | 0.000700 | $865.29 | $0.61 |
| AUX-09 | CONCRETO HECHO EN OBRA F'c = 100 KG/CM2 AGREGADO MAX. 3/4" R.N. | m3 | 0.000700 | $865.29 | $0.61 |
| AUX-09 | CONCRETO HECHO EN OBRA F'c = 100 KG/CM2 AGREGADO MAX. 3/4" R.N. | m3 | 0.000700 | $865.29 | $0.61 |
| Suma de Auxiliar | | | | $6.06 |
| Costo Directo | | | | $77.95 |