| SEÑ-002 | FONDO PARA LETRAS Y NUMEROS IDENTIFICADORES DE 0.25 M DE ANCHO EN TODO EL CONTORNO DE LA COLUMNA, COLOR SEGÚN MUESTRA APROBADA POR SUPERVISION, DEACUERDO AL NIVEL DE ESTACIONAMIENTO. | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| E-PINT-TERMO | PINTURA TERMOPLASTICA | litro | 0.250000 | $61.89 | $15.47 |
| E-THINNER POLI | THINNER POLIFORM | litro | 0.070000 | $30.00 | $2.10 |
| Suma de Material | $17.57 | ||||
| Mano de Obra | |||||
| 02-0710 | CUADRILLA No 71 ( 1 PINTOR + 1 AYUDANTE DE PINTOR ) | jor | 0.025000 | $926.46 | $23.16 |
| Suma de Mano de Obra | $23.16 | ||||
| Costo Directo | $40.73 |