| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 267 | ESPECIFICACION PARTICULAR No. 135 | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MA015 | Agua Limpia | M3 | 0.050000 | $62.50 | $3.13 |
| MA168 | Fertilizante Para Plantas De Ornato | KG | 1.000000 | $45.00 | $45.00 |
| MA324 | Tierra Negra Vegetal | M3 | 3.000000 | $200.00 | $600.00 |
| MA184 | Impermeabilizante Para Mortero Sika-1 | LT | 0.250000 | $35.00 | $8.75 |
| MA119 | Concreto Premezclado F´C= 150 Kg/Cm2, Ag | M3 | 0.400000 | $894.00 | $357.60 |
| MA207 | Madera De Pino De Segunda | PT | 9.000000 | $10.00 | $90.00 |
| MA180 | Gravilla Limpia | M3 | 0.250000 | $230.00 | $57.50 |
| MA034 | Block Hueco de 15 x 20 x 40 cm | PZA | 40.000000 | $6.40 | $256.00 |
| MA089 | Cemento Gris Portland Normal Tipo I | TON | 0.100000 | $1,879.31 | $187.93 |
| MA015 | Agua Limpia | M3 | 0.125000 | $62.50 | $7.81 |
| MA333 | Triplay De Pino De 16 Mm. De Espesor | M2 | 0.250000 | $142.00 | $35.50 |
| Suma de Material | $1,649.22 | ||||
| Mano de Obra | |||||
| CUAD-VACCON | Personal: Albañil+3 Ayudante Gral | JOR | 1.000000 | $2,120.47 | $2,120.47 |
| Suma de Mano de Obra | $2,120.47 | ||||
| Equipo | |||||
| BEQUI-JAR | EQUIPO: PARA JARDINERAS | JOR | 2.000000 | $140.78 | $281.56 |
| %MOHM | Herramienta menor | (%)MO | 0.020000 | $0.00 | $0.00 |
| %MOES | Equipo de Seguridad Personal | (%)MO | 0.050000 | $0.00 | $0.00 |
| Suma de Equipo | $281.56 | ||||
| Concepto | |||||
| C0120063 | Habilitado Y Colocacion De Acero De Refu | TON | 0.020220 | $16,510.15 | $333.84 |
| MORT14 | Mortero Cemento Arena Proporcion 1:4 | M3 | 0.400000 | $1,110.43 | $444.17 |
| C0120067 | Habilitado Y Colocacion De Acero De Refu | TON | 0.002818 | $16,072.87 | $45.29 |
| Suma de Concepto | $823.30 | ||||
| Costo Directo | $4,874.55 |