| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 239 | ESPECIFICACIÓN PARTICULAR No. 107 | PZA. |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MA279 | Remache Pop De Aluminio Natural, (Bolsa | BOLSA | 0.100000 | $19.00 | $1.90 |
| MA129 | Contramarco De Aluminio Natural 3" | M | 4.800000 | $71.80 | $344.64 |
| MA190 | Junquillo De Aluminio Natural | M | 14.600000 | $23.04 | $336.38 |
| MA308 | Taquete De Plastico De 1/4"Ø | PZA | 4.000000 | $0.65 | $2.60 |
| MA211 | Marco De Aluminio Natural 3" | M | 4.200000 | $71.80 | $301.56 |
| MA224 | Panelart De 6 Mm De Espesor | M2 | 1.280000 | $62.62 | $80.15 |
| MA237 | Pijas De 10 X 2" | PZA | 16.000000 | $1.00 | $16.00 |
| Suma de Material | $1,083.24 | ||||
| Mano de Obra | |||||
| CUADCANCELERIA | Mano De Obra: 1 Aluminiero + 2 Ayudantes | JORN | 0.500000 | $1,772.17 | $886.09 |
| Suma de Mano de Obra | $886.09 | ||||
| Equipo | |||||
| %MOES | Equipo de Seguridad Personal | (%)MO | 0.050000 | $0.00 | $0.00 |
| %MOHM | Herramienta menor | (%)MO | 0.020000 | $0.00 | $0.00 |
| BEQCANCELERIA | Equipo: Taladro, Andamio, Camioneta, Gen | HR | 0.500000 | $160.89 | $80.45 |
| Suma de Equipo | $80.45 | ||||
| Costo Directo | $2,049.77 |