| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 334 | ESPECIFICACIÓN PARTICULAR No. 202 | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MA019 | Alambre Recocido No.18 | KG | 0.240000 | $10.26 | $2.46 |
| MA180 | Gravilla Limpia | M3 | 0.007965 | $230.00 | $1.83 |
| MA179 | Grava Lavada Para Concretos Tamaño 3/4" | M3 | 0.009650 | $345.00 | $3.33 |
| MA089 | Cemento Gris Portland Normal Tipo I | TON | 0.005520 | $1,879.31 | $10.37 |
| MA020 | Alambron 1/4" Diam. | KG | 0.001000 | $9.05 | $0.01 |
| MA140 | Desmoldante Para Cimbra | LT | 0.150000 | $12.00 | $1.80 |
| MA101 | Clavo De 2" A 4" | KG | 0.125000 | $12.68 | $1.59 |
| MA207 | Madera De Pino De Segunda | PT | 0.600000 | $10.00 | $6.00 |
| MA366 | Varilla Corrugada F`Y=4,200 Kg/Cm2 No. 3 | TON | 0.002562 | $9,656.00 | $24.74 |
| MA015 | Agua Limpia | M3 | 0.005250 | $62.50 | $0.33 |
| Suma de Material | $52.46 | ||||
| Mano de Obra | |||||
| CUAD201 | Mano De Obra: .3 Albañil + .3 Carpintero | JORN | 0.033333 | $3,242.31 | $108.08 |
| Suma de Mano de Obra | $108.08 | ||||
| Equipo | |||||
| %MOES | Equipo de Seguridad Personal | (%)MO | 0.050000 | $0.00 | $0.00 |
| %MOHM | Herramienta menor | (%)MO | 0.020000 | $0.00 | $0.00 |
| MAQ201 | Equipo: Revolvedora, Vibrador, Cortadora | HR | 0.266667 | $191.24 | $51.00 |
| Suma de Equipo | $51.00 | ||||
| Costo Directo | $211.53 |