| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 75 | ESPECIFICACIÓN PARTICULAR No. 34 | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MA019 | Alambre Recocido No.18 | KG | 0.018000 | $10.26 | $0.18 |
| MA204 | Lubricante Para Cuerdas A Base De Litio | LT | 0.001500 | $45.00 | $0.07 |
| MA099 | Cinta Teflon 3/4" X 8 Mt | PZA | 0.021000 | $9.13 | $0.19 |
| MA352 | Tubo Conduit Galv. De 3/4" Ø, Ced 40 | M | 1.020000 | $54.26 | $55.35 |
| Suma de Material | $55.79 | ||||
| Mano de Obra | |||||
| CUAJ-01020EL | Personal: 1 Electrico + 2 Ayudantes | JOR | 0.022727 | $1,772.17 | $40.28 |
| Suma de Mano de Obra | $40.28 | ||||
| Equipo | |||||
| %MOHM | Herramienta menor | (%)MO | 0.020000 | $0.00 | $0.00 |
| %MOES | Equipo de Seguridad Personal | (%)MO | 0.050000 | $0.00 | $0.00 |
| BEQUI-DUCTSUBT10 | EQUIPO: INSTALAR TUBERIA CONDUIT SUBTERR | HR | 0.181818 | $119.85 | $21.79 |
| Suma de Equipo | $21.79 | ||||
| Costo Directo | $117.86 |