| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 248 | ESPECIFICACIÓN PARTICULAR No. 116 | JTA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MA009 | Adelgazador Para Pinturas | LT | 0.250000 | $44.48 | $11.12 |
| MA097 | Cinta Para Recubrimiento De 6" X 200' | ROLLO | 0.250000 | $396.00 | $99.00 |
| MA143 | Disco Abrasivo Para Desvaste De 8"Ø X 1/ | PZA | 0.333333 | $48.00 | $16.00 |
| MA098 | Cinta Para Recubrimiento De 6" X 50' | ROLLO | 0.250000 | $285.00 | $71.25 |
| MA027 | Arena Silica | TON | 0.030000 | $1,500.00 | $45.00 |
| MA250 | Primario Rp-5 | LT | 3.000000 | $86.95 | $260.85 |
| MA198 | Liquidos Penetrantes | M | 1.000000 | $80.00 | $80.00 |
| MA008 | Acetileno | KG | 0.200000 | $210.00 | $42.00 |
| MA244 | Placa De Acero Al Carbon De 1/2" De Espe | KG | 10.200000 | $19.19 | $195.74 |
| MA288 | Soldadura E-6010 Y E-7018 De 1/8" A 3/ | KG | 3.000000 | $38.50 | $115.50 |
| MA222 | Oxigeno | M3 | 1.000000 | $70.00 | $70.00 |
| MA083 | Carda Circular Trenzada | PZA | 0.333333 | $190.00 | $63.33 |
| Suma de Material | $1,069.79 | ||||
| Mano de Obra | |||||
| CUADSOLD1 | Mano De Obra: 1 Soldador+3 Ayudantes+0.3 | JORN | 0.125000 | $5,222.35 | $652.79 |
| Suma de Mano de Obra | $652.79 | ||||
| Equipo | |||||
| %MOHM | Herramienta menor | (%)MO | 0.020000 | $0.00 | $0.00 |
| %MOES | Equipo de Seguridad Personal | (%)MO | 0.050000 | $0.00 | $0.00 |
| BEQSOLD | EQUIPO: SAND BLAST, PINTURA, SOLDADORA | HR | 0.125000 | $999.62 | $124.95 |
| Suma de Equipo | $124.95 | ||||
| Costo Directo | $1,847.54 |