| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 73 | ESPECIFICACIÓN PARTICULAR No. 32 | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MA020 | Alambron 1/4" Diam. | KG | 0.002000 | $9.05 | $0.02 |
| MA015 | Agua Limpia | M3 | 0.015000 | $62.50 | $0.94 |
| MA020 | Alambron 1/4" Diam. | KG | 1.900000 | $9.05 | $17.20 |
| MA015 | Agua Limpia | M3 | 0.020000 | $62.50 | $1.25 |
| MA101 | Clavo De 2" A 4" | KG | 0.100000 | $12.68 | $1.27 |
| MA213 | Membrana De Curado, Color Rojo | LT | 0.030000 | $16.83 | $0.50 |
| MA366 | Varilla Corrugada F`Y=4,200 Kg/Cm2 No. 3 | TON | 0.002300 | $9,656.00 | $22.21 |
| MA207 | Madera De Pino De Segunda | PT | 2.500000 | $10.00 | $25.00 |
| MA091 | Chaflan De Madera De 1" X 1" | M | 0.250000 | $1.90 | $0.48 |
| MA019 | Alambre Recocido No.18 | KG | 0.175000 | $10.26 | $1.80 |
| DIESEL | Diesel | LT | 0.200000 | $7.38 | $1.48 |
| Suma de Material | $72.13 | ||||
| Mano de Obra | |||||
| CUAJ-00120A | Mano De Obra: 1 Albañil + 2 Ayudantes | JORN | 0.147059 | $1,772.16 | $260.61 |
| Suma de Mano de Obra | $260.61 | ||||
| Equipo | |||||
| BEQUI-CTDVAR1" | Equipo: Cortadora De Varilla, Camioneta | HR | 0.166667 | $119.85 | $19.98 |
| %MOES | Equipo de Seguridad Personal | (%)MO | 0.050000 | $0.00 | $0.00 |
| %MOHM | Herramienta menor | (%)MO | 0.020000 | $0.00 | $0.00 |
| BEQUI-VIB10 | Equipo: Vibrador Para Concreto, A Gasoli | HR | 0.100000 | $93.86 | $9.39 |
| Suma de Equipo | $29.36 | ||||
| Concepto | |||||
| BACON200 | Basico: Elab. Concreto F'c= 200 Kg/Cm2, | M3 | 0.101500 | $1,405.73 | $142.68 |
| Suma de Concepto | $142.68 | ||||
| Costo Directo | $504.78 |