| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 262 | ESPECIFICACION PARTICULAR No. 130 | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MA019 | Alambre Recocido No.18 | KG | 0.250000 | $10.26 | $2.57 |
| MA101 | Clavo De 2" A 4" | KG | 0.150000 | $12.68 | $1.90 |
| MA191 | Lámina Galvanizada Cal. 20 | KG | 15.000000 | $16.60 | $249.00 |
| MA091 | Chaflan De Madera De 1" X 1" | M | 1.000000 | $1.90 | $1.90 |
| MA140 | Desmoldante Para Cimbra | LT | 0.250000 | $12.00 | $3.00 |
| MA179 | Grava Lavada Para Concretos Tamaño 3/4" | M3 | 0.067000 | $345.00 | $23.12 |
| MA015 | Agua Limpia | M3 | 0.020000 | $62.50 | $1.25 |
| MA207 | Madera De Pino De Segunda | PT | 3.000000 | $10.00 | $30.00 |
| MA366 | Varilla Corrugada F`Y=4,200 Kg/Cm2 No. 3 | TON | 0.004500 | $9,656.00 | $43.45 |
| MA180 | Gravilla Limpia | M3 | 0.056000 | $230.00 | $12.88 |
| MA089 | Cemento Gris Portland Normal Tipo I | TON | 0.036000 | $1,879.31 | $67.66 |
| Suma de Material | $436.72 | ||||
| Mano de Obra | |||||
| CUAD95 | PERSONAL: ELABORACION PASO DE DUCTO | JORN | 1.000000 | $5,148.39 | $5,148.39 |
| Suma de Mano de Obra | $5,148.39 | ||||
| Equipo | |||||
| %MOHM | Herramienta menor | (%)MO | 0.020000 | $0.00 | $0.00 |
| %MOES | Equipo de Seguridad Personal | (%)MO | 0.050000 | $0.00 | $0.00 |
| BEQUI-PASODU | EQUIPO: PARA PASO DE DUCTO | HR | 2.000000 | $222.12 | $444.24 |
| Suma de Equipo | $444.24 | ||||
| Costo Directo | $6,029.35 |