| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| UV 504 | PISO DE CEMENTO LAVADO DE 5.0 CM. DE ESPESOR MÁXIMO , INCLUYE MATERIALES, MANO DE OBRA, HERRAMIENTA, EQUIPO, LIMPIEZA DURANTE LA OBRA Y AL FINAL Y TODO LO NECESARIO APRA SU CORRECTA EJECUCIÓN (P.U.O.T.) | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ALAMBRE1. | ALAMBRE RECOCIDO calibre 18 | KG | 0.085000 | $11.30 | $0.96 |
| MADERA DE PINO 3A | madera para estacas | pt | 0.250000 | $7.00 | $1.75 |
| CLAVO (VARIAS MED.) | CLAVO PARA MADERA VARIAS MEDIDAS | KG | 0.100000 | $13.75 | $1.38 |
| DIESEL | DIESEL | LT | 0.150000 | $5.06 | $0.76 |
| Suma de Material | $4.84 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.104965 | $634.95 | $66.65 |
| Suma de Mano de Obra | $66.65 | ||||
| Auxiliar | |||||
| CONCRETO F-C=200 H/O | CONCRETO H.O. F'C=200 KG/CM2, R.N. AGR. MAX. 3/4" | M3 | 0.105000 | $955.25 | $100.30 |
| Suma de Auxiliar | $100.30 | ||||
| Costo Directo | $171.79 |