| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| EST-04 | LOSA DE CONCRETO F'C 250 KG/CM2, DE 10 CMS DE ESPESOR ARMADA CON VARILLA No. 3 @ 15 CMS. , ACABADO NORMAL, INC. MATERIALES, MANO DE OBRA, HERRAMIENTA, DESPERDICIOS Y TODO LO NECESARIO PARA SU CORRECTA EJECUCIÓN. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACERO VARIOS DIAM. | ACERO REF.VARIAS DIM | KG | 6.050000 | $8.50 | $51.43 |
| ALAMBRE RECOC 18 | ALAMBRE RECOCIDO # 18 | KG | 0.178560 | $14.87 | $2.66 |
| CONC.PREMEZ.F´C=300 | Concreto Premezclado F'c=300 Kg/cm2 A.M. 3/4" rev 13-14 | M3 | 0.110000 | $820.00 | $90.20 |
| AGUA | agua | M3 | 0.050000 | $40.00 | $2.00 |
| POLIN 3.5" X 3.5" | MADERA DE PINO DE 3A. EN POLIN DE 3.5" X 3.5" | PT | 1.500000 | $7.50 | $11.25 |
| BARROTE 1.5" X 3.5" | MADERA DE PINO DE 3A. EN BARROTE DE 1.5" X 3.5" | PT | 1.500000 | $5.60 | $8.40 |
| CIMBRAPLAY 16 MM | cimbraplay de 16 mm | M2 | 0.333000 | $90.00 | $29.97 |
| DIESEL | diesel pemex | Lt | 0.580000 | $6.50 | $3.77 |
| CLAVOS | VARIAS MEDIDAS NORMAL .004KG/PZA PROM. | KG | 0.300000 | $17.50 | $5.25 |
| Suma de Material | $204.92 | ||||
| Mano de Obra | |||||
| CUAD 18 | Cuadrilla No. 18 ( 1 Of. Fierrero + 1Ayudante). | jor | 0.008333 | $799.88 | $6.67 |
| CUAD 05 | ( 1 ALBAÑIL + 5 PEONES ) | jor | 0.028571 | $2,105.73 | $60.16 |
| 2CUA CARPINTERO 2 | (1 Oficial carpintero de obra negra + 1 ayte.) | JOR | 0.143472 | $815.26 | $116.97 |
| Suma de Mano de Obra | $183.80 | ||||
| Herramienta | |||||
| HE003 | Andamios metálicos tipo torre | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| BOMBA PLUMA | Bomba pluma para concreto con diámetro hasta 4" (102mm) | M3 | 0.110000 | $140.00 | $15.40 |
| VIBRADOR P/CONCRETO | Vibrador para concreto Mot. Kohler 4 H.Con operador. | HR | 0.075000 | $56.24 | $4.22 |
| GRUA TORRE | GRUA TORRE TREPADORA MODELO GT 116 | hora | 0.099530 | $455.80 | $45.37 |
| ELEVADOR | ELEVADOR MCA. CAMAC | hora | 0.151230 | $300.00 | $45.37 |
| Suma de Equipo | $110.35 | ||||
| Costo Directo | $499.07 |