| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4A | CIMBRA APARENTE EN TRABE | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.250000 | $92.00 | $23.00 |
| CIMBRA-011 | CHAFLAN DE 1" | ML | 2.000000 | $4.00 | $8.00 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 3.800000 | $10.00 | $38.00 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.090000 | $17.10 | $1.54 |
| COMBUSTIBLE 05 | DIESEL | LT | 0.500000 | $5.00 | $2.50 |
| Suma de Material | $73.04 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 17 | (1 Of. Carpintero de banco + 1 Ayte) | Jor | 0.120000 | $599.53 | $71.94 |
| Suma de Mano de Obra | $71.94 | ||||
| Costo Directo | $144.98 |