| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 047G11A04 | De f'c = 150 kg/cm2 en guarniciones | m3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO F-C=150 H/O | Concreto f'c=150 kg/cm2 hecho en obra agregado maximo gravilla 3/4" O 1 1/2" | M3. | 1.050000 | $898.31 | $943.23 |
| CONCRETO F-C=150 H/O | Concreto f'c=150 kg/cm2 hecho en obra agregado maximo gravilla 3/4" O 1 1/2" | M3. | 1.050000 | $898.31 | $943.23 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 4.500000 | $5.00 | $22.50 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 4.500000 | $5.00 | $22.50 |
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 1.000000 | $69.00 | $69.00 |
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 1.000000 | $69.00 | $69.00 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.020000 | $8.00 | $0.16 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.020000 | $8.00 | $0.16 |
| CONCRETO PRE-03 | BOMBA PARA CONCRETO | M3 | 1.050000 | $120.00 | $126.00 |
| CONCRETO PRE-03 | BOMBA PARA CONCRETO | M3 | 1.050000 | $120.00 | $126.00 |
| Suma de Material | $2,321.77 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | Jor | 0.150000 | $468.89 | $70.33 |
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | Jor | 0.150000 | $468.89 | $70.33 |
| CUADRILLA NO. 11 | (1 Of. Carpintero O.N. + 1Ayte). | Jor | 0.166667 | $483.34 | $80.56 |
| CUADRILLA NO. 11 | (1 Of. Carpintero O.N. + 1Ayte). | Jor | 0.166667 | $483.34 | $80.56 |
| Suma de Mano de Obra | $301.78 | ||||
| Equipo | |||||
| MAQUINARIA-13 | VIBRADOR CONCRETO | HR | 0.200000 | $18.99 | $3.80 |
| MAQUINARIA-13 | VIBRADOR CONCRETO | HR | 0.200000 | $18.99 | $3.80 |
| Suma de Equipo | $7.60 | ||||
| Auxiliar | |||||
| ANDAMIO 2 MTS | ANDAMIO DE 2.00 MTS DE ALTURA | DIA | 0.150000 | $18.76 | $2.81 |
| ANDAMIO 2 MTS | ANDAMIO DE 2.00 MTS DE ALTURA | DIA | 0.150000 | $18.76 | $2.81 |
| Suma de Auxiliar | $5.63 | ||||
| Costo Directo | $2,636.78 |