| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| S/C-01 | De f`c=150kg/cm2 en banquetas | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIMBRA-04 | MADERA DE PINO | PT | 0.600000 | $6.00 | $3.60 |
| CIMBRA-01 | CIMBRAPLAY | M2 | 0.100000 | $100.00 | $10.00 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.250000 | $8.00 | $2.00 |
| Suma de Material | $15.60 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | Jor | 0.750000 | $468.89 | $351.67 |
| Suma de Mano de Obra | $351.67 | ||||
| Auxiliar | |||||
| CONCRETO HECHO 150 | CONCRETO HECHO EN OBRA DE 150 KG/CM2 | M3 | 1.100000 | $799.86 | $879.85 |
| Suma de Auxiliar | $879.85 | ||||
| Costo Directo | $1,247.11 |