| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| CONESP-200 | CONCRETO EN ESTRUCTURA F'C=250 KG/CM2 PREMEZCLADO RESISTENCIA NORMAL VACIADO CON BOMBA, REVENIMIENTO DE 14 CM., AGREGADO MAXIMO 3/4", INCLUYE: MATERIALES, EQUIPO, HERRAMIENTA, MANO DE OBRA, VIBRADO, CURADO Y DEMAS CARGOS CORRESPONDIENTES. | M3. |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 0900-12 | CONCRETO PREMEZC.RN F'C=250 KG/CM2 AGREGADO MAXIMO 3/4" (A) | m3 | 1.030000 | $995.38 | $1,025.24 |
| 0901-00 | SOBRE PRECIO POR REV. 14 CM AGREG. 3/4" APTO PARABOMB.(A) | M3 | 1.030000 | $123.00 | $126.69 |
| 0601-05 | BOMBEO DE CONCRETO C/BOMBA EST. HASTA 5 NIVEL (15M ALTURA) | M3 | 1.030000 | $150.00 | $154.50 |
| Suma de Material | $1,306.43 | ||||
| Mano de Obra | |||||
| 02-1570 | CUADRILLA No. 157 (DE COLOCACION DE CONCRETO) | jor | 0.020833 | $2,787.81 | $58.08 |
| Suma de Mano de Obra | $58.08 | ||||
| Equipo | |||||
| 03-4010 | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | hora | 0.400000 | $14.04 | $5.62 |
| Suma de Equipo | $5.62 | ||||
| Auxiliar | |||||
| 00-0050 | AGUA ACARREADA EN PIPA; INCLUYE TRANSPORTE A OBRA Y PAGO DE REGALIAS. | m3 | 0.060000 | $31.76 | $1.91 |
| Suma de Auxiliar | $1.91 | ||||
| Costo Directo | $1,372.03 |