| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| AA3203.010 | SOPORTE PARA TUBERÍAS VERTICALES FABRICADA CON ANGULO O CANAL DE ACERO DE 0.60 MTS. DE LONGITUD (+/- 0.05 MTS.), CON 2 ABRAZADERA B-LINE B2417, SOPORTE PARA TUBERÍAS VERTICALES FABRICADA CON ANGULO O CANAL DE ACERO @2.0 MTS. (APLICA ALCANCE GENÉRICO AA3203.000)P.U.O.T. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| UNICANALPS-200H | CANAL POWER STRUT PS-200H | PZA | 0.238100 | $189.00 | $45.00 |
| VARILLA ROSCADA 3/8" | VARILLA ROSCADA DE 3/8 PLG X 3.0 M | PIEZA | 1.078680 | $30.61 | $33.02 |
| TAQ-SCI-3/8" | TAQUETE TIPO SCI DE 3/8" | PZA | 2.000000 | $2.20 | $4.40 |
| TUERCA HEX 3/8-- | Tuerca hexagonal de 3/8'' de diametro | PZA | 4.000000 | $0.55 | $2.20 |
| ARAND-GALV-3/8" | ARANDELA PLANA GALVANIZADA DE 3/8" | PZA | 4.000000 | $0.80 | $3.20 |
| ABRAZ LU 4 | ABRAZADERA B-LINE B2417 | PZA | 1.000000 | $28.00 | $28.00 |
| ABRAZ LU 6" | ABRAZADERA B-LINE B2417 | PZA | 1.000000 | $34.00 | $34.00 |
| ANDAMIO | TORRE DE TRABAJO DE 5 M DE ALTURA CON RUEDAS | R/D | 0.035950 | $30.50 | $1.10 |
| Suma de Material | $150.92 | ||||
| Mano de Obra | |||||
| INS CUAD A ACONDIC | Cuadrilla de aire acondicionado | Jor | 0.224300 | $1,807.03 | $405.32 |
| Suma de Mano de Obra | $405.32 | ||||
| Costo Directo | $556.23 |