| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ESTVIG-010102 | SUMINISTRO, FABRICACION Y MONTAJE DE VIGA IPR V-1 CON PESOS DE 160.50 KG/M INCLUYE: TRAZO, NIVELACION, CORTES, AJUSTES, ACARREOS, ELEVACION, SOLDADURA, LIJADO ESMERILADO, MATERIAL, MANO DE OBRA, EQUIPO Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION. | KG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| IR 762X160.50 | VIGA IR A-36 762 x 160.50 KG/ML | kg | 1.080000 | $10.00 | $10.80 |
| 00-0009 | CONSUMOS DE FABRICACION EN ESTRUCTURA METALICA | (%)m | 0.060000 | $0.00 | $0.00 |
| 00-0007 | CONSUMOS DE MONTAJE EN ESTRUCTURA METALICA | (%)m | 0.060000 | $0.00 | $0.00 |
| Suma de Material | $10.80 | ||||
| Mano de Obra | |||||
| 00-0005 | CONTROL DE CALIDAD | (%)mo | 0.020000 | $0.00 | $0.00 |
| 02-1510 | CUADRILLA No. 151 (PARA FABRICACION DE ESTRUCTURA METALICA.) | jor | 0.000870 | $5,742.08 | $5.00 |
| 02-1520 | CUADRILLA No. 152 (PARA MONTAJE DE ESTRUCTURA METALICA) | jor | 0.000860 | $5,087.29 | $4.38 |
| Suma de Mano de Obra | $9.37 | ||||
| Equipo | |||||
| 03-6100 | MAQUINA DE SOLDAR ELECTRICA | hora | 0.030000 | $5.74 | $0.17 |
| 03-8070 | METALERO | hora | 0.006000 | $18.30 | $0.11 |
| 03-4220 | EQUIPO DE CORTE DE OXI-ACETILENO CON ACCESORIOS HARRIS | hora | 0.008700 | $21.81 | $0.19 |
| 03-8050 | GRUA VIAJERA | hora | 0.000450 | $43.17 | $0.02 |
| 03-6050 | GRUA PETTIBONE 25,000 LBS. | hora | 0.000400 | $914.70 | $0.37 |
| Suma de Equipo | $0.86 | ||||
| Auxiliar | |||||
| 00-0011 | FLETE DEL TALLER DE ESTRUCTURAS A LA OBRA | kg | 1.000000 | $0.50 | $0.50 |
| Suma de Auxiliar | $0.50 | ||||
| Costo Directo | $21.53 |