| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 02-050-301 | GUARNICION TRAPEZOIDAL DE 20X25X45 CMS. DE CONCRETO PREMEZCLADO F'C=200 KG/CM2 T.M.A. 3/4" ARMADA CON 6 VARILLAS DEL No. 3 (3/8") Y ESTRIBOS DEL No. 2 (1/4") @ 15 CMS. (VER ESP HTT 02-010) | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONC. PREMEZ F-C=200 | CONCRETO PREMEZCLADO F'C=200KG/CM2 | M3 | 0.075000 | $987.00 | $74.03 |
| CIMBRAPLAY 16MM. | CIMBRAPLAY 16MM. | M2 | 0.146700 | $115.00 | $16.87 |
| MADERA PINO 3A | MADERA PINO 3A DIFERENTES DIMENSIONES | pt | 2.000000 | $7.75 | $15.50 |
| ACERO DE REF. VARIOS | ACERO DE REFUERZO VARIOS DIAMETROS | KG | 4.100000 | $11.00 | $45.10 |
| ALAMBRE RECOCIDO. | ALAMBRE RECOCIDO. | KG | 0.040000 | $13.00 | $0.52 |
| CLAVO DIF. MEDIDAS | CLAVO DIFERENTES MEDIDAS | KG | 0.125000 | $17.00 | $2.13 |
| DESMOLDANTE | DESMOLDANTE PARA CIMBRA | LT | 0.500000 | $25.00 | $12.50 |
| Suma de Material | $166.64 | ||||
| Mano de Obra | |||||
| CUADRILLA 005 VANG | Cuadrilla No 5 (1 AlbañÃl + 1 Ayudante general ) | JOR | 0.100000 | $962.82 | $96.28 |
| CUADRILLA 001 VANG | Cuadrilla No 1. (1 Ayudante General) | JOR | 0.040000 | $385.90 | $15.44 |
| Suma de Mano de Obra | $111.72 | ||||
| Equipo | |||||
| VBRADOR CONC. | VIBRADOR PARA CONCRETO DE GASOLINA | hora | 0.082400 | $77.30 | $6.37 |
| Suma de Equipo | $6.37 | ||||
| Costo Directo | $284.73 |