| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| *TEMP1058 | CONCRETO PREMEZCLADO FC=250 KG/CM2 CON IMPERMEABILIZANTE INTEGRAL | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| BOMBEO CONCRETO | BOMBEO DE CONCRETO | M3 | 1.050000 | $147.25 | $154.61 |
| IMPERM. INTEGRAL | IMPERMEABILIZANTE INTEGRAL | M3 | 1.050000 | $92.00 | $96.60 |
| CONC.PREMEZ.F-C 250 | CONCRETO PREMEZCLADO RESISTENCIA NORMAL F'C = 250 KG/CM2, T.M.A. 3/4", INCL REVENIMIENTO | M3 | 1.050000 | $874.00 | $917.70 |
| AGUA | AGUA | M3 | 0.095000 | $46.00 | $4.37 |
| Suma de Material | $1,173.28 | ||||
| Mano de Obra | |||||
| CUAD OC 05 | CUAD. 1 ALBAÑIL + 5 PEONES | jor | 0.066667 | $1,989.44 | $132.63 |
| Suma de Mano de Obra | $132.63 | ||||
| Equipo | |||||
| AVIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | HR | 0.189500 | $70.42 | $13.34 |
| Suma de Equipo | $13.34 | ||||
| Costo Directo | $1,319.26 |