| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| *TEMP1017 | Banqueta de concreto f'c= 150 kg/cm2 de 10 cm de espesor | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MALLA ELECTRO | MALLA ELECTR. 6X6/6-6 | M2 | 1.100000 | $29.00 | $31.90 |
| 1900-10 | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 1.300000 | $8.62 | $11.21 |
| 0100-00 | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.040000 | $14.38 | $0.58 |
| ACARREO INT.DE AGUA | Agua | m3 | 0.067000 | $46.00 | $3.08 |
| Suma de Material | $46.76 | ||||
| Mano de Obra | |||||
| CUAD OC 02 | CUAD. 1 OP. DE EQUIPO MENOR. | JOR | 0.100000 | $363.12 | $36.31 |
| Suma de Mano de Obra | $36.31 | ||||
| Auxiliar | |||||
| 03-2170 | CONCRETO HECHO EN OBRA F'C=150 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 1 1/2" | M3 | 0.105000 | $914.32 | $96.00 |
| Suma de Auxiliar | $96.00 | ||||
| Costo Directo | $179.08 |