| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| *TEMP1051 | Columna de concreto armada de 25 x 25 cm de 3.50 mts de altura | pza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO DE F-C 200 | concreto premezclado de f´c = 200 kg / cm2 | m3 | 0.230000 | $855.00 | $196.65 |
| 1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1" X 4" | PT | 5.600000 | $8.62 | $48.27 |
| ACERO | VARILLA A. R. FY=4200 KG/CM2. DEL No. 3 AL 12 | kg | 30.360000 | $10.20 | $309.67 |
| 0082-00 | ALAMBRE RECOCIDO NO. 16 | KG | 0.910000 | $15.20 | $13.83 |
| 0100-00 | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.875000 | $14.38 | $12.58 |
| 0950-05 | DIESEL | LT | 2.800000 | $5.98 | $16.74 |
| Suma de Material | $597.75 | ||||
| Mano de Obra | |||||
| CUAD OC 02 | CUAD. 1 OP. DE EQUIPO MENOR. | JOR | 0.583310 | $363.12 | $211.81 |
| Suma de Mano de Obra | $211.81 | ||||
| Auxiliar | |||||
| 03-7010 | ANDAMIO DE CABALLETES Y TABLONES CONSTRUIDO CON MADERA DE PINO DE 3¬ USADO PARA ALTURAS DE 1.50 A 3.00 M. | PZA | 0.636300 | $435.15 | $276.89 |
| Suma de Auxiliar | $276.89 | ||||
| Costo Directo | $1,086.45 |