| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2.08 | SUMINISTRO Y DE CONCRETO PREMEZCLADO F'C=250 KG/CM2 R.N. TMA. 3/4" PARA SER COLOCADO CON EL SISTEMA TREMIE " EN PILAS DE CIMENTACION, CON SUPERFLUIDIFICANTES REVENIMIENTO 18, INCLUYE: SUMINISTRO DEL MATERIAL, VOLUMEN ADICIONAL POR EL DEBORDE DE PAREDES DE LA PILA, Y DESPERDICIOS. | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONC.PREMEZ.F-C 250 | CONCRETO PREMEZCLADO RESISTENCIA NORMAL F'C = 250 KG/CM2, T.M.A. 3/4", INCL REVENIMIENTO | M3 | 1.200000 | $874.00 | $1,048.80 |
| CONC.PREMEZ.F-C 250 | CONCRETO PREMEZCLADO RESISTENCIA NORMAL F'C = 250 KG/CM2, T.M.A. 3/4", INCL REVENIMIENTO | M3 | 1.200000 | $874.00 | $1,048.80 |
| REVENIMIENTO P/CONC | REVENIMIENTO P/CONC | M3 | 1.200000 | $86.25 | $103.50 |
| REVENIMIENTO P/CONC | REVENIMIENTO P/CONC | M3 | 1.200000 | $86.25 | $103.50 |
| BOMBEO CONCRETO | BOMBEO DE CONCRETO | M3 | 1.200000 | $147.25 | $176.70 |
| BOMBEO CONCRETO | BOMBEO DE CONCRETO | M3 | 1.200000 | $147.25 | $176.70 |
| Suma de Material | $2,658.00 | ||||
| Mano de Obra | |||||
| CUAD OC 05 | CUAD. 1 ALBAÑIL + 5 PEONES | jor | 0.010000 | $1,989.44 | $19.89 |
| CUAD OC 05 | CUAD. 1 ALBAÑIL + 5 PEONES | jor | 0.010000 | $1,989.44 | $19.89 |
| Suma de Mano de Obra | $39.79 | ||||
| Costo Directo | $2,697.79 |