| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 5.07 | ACABADO PULIDO EN LOSA DE CONCRETO CON ALLANADORA MECANICA, INCLUYE, MATERIALES DE CONSUMO, MANO DE OBRA, HERRAMIENTA Y EQUIPO. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGUA | AGUA | M3 | 0.040000 | $46.00 | $1.84 |
| AGUA | AGUA | M3 | 0.040000 | $46.00 | $1.84 |
| AGREGADO 8 | CEMENTO NORMAL GRIS TIPO I EN SACO | TON | 0.001200 | $1,800.00 | $2.16 |
| AGREGADO 8 | CEMENTO NORMAL GRIS TIPO I EN SACO | TON | 0.001200 | $1,800.00 | $2.16 |
| CIMBRAG | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 0.500000 | $7.50 | $3.75 |
| CIMBRAG | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 0.500000 | $7.50 | $3.75 |
| Suma de Material | $15.50 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.040000 | $768.76 | $30.75 |
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.040000 | $768.76 | $30.75 |
| Suma de Mano de Obra | $61.50 | ||||
| Equipo | |||||
| ALLANADORA MECANIC. | ALLANADORA MECANICA CON ASPAS | hora | 0.028571 | $63.76 | $1.82 |
| ALLANADORA MECANIC. | ALLANADORA MECANICA CON ASPAS | hora | 0.028571 | $63.76 | $1.82 |
| Suma de Equipo | $3.64 | ||||
| Costo Directo | $80.64 |