| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Concepto | | | | |
| TOR-207A | CIMBRA APARENTE EN RAMPAS DE ESCALERA A BASE DE MADERA DE PINO INCLUYE: CIMBRA, DESCIMBRA, ALTURA VARIABLE DE POLINES POR APOYO EN LA PENDIENTE DE RAMPA, MAYOR DIFICULTAD DE ARMADO POR PENDIENTE, ACARREOS, DESMOLDANTE, DESPERDICIOS, MATERIALES, MANO DE OBRA, HERRAMIENTA Y EQUIPO (P.U.O.T.). | M2 | 1.000000 | $179.40 | $179.40 |
| TOR-207A | CIMBRA APARENTE EN RAMPAS DE ESCALERA A BASE DE MADERA DE PINO INCLUYE: CIMBRA, DESCIMBRA, ALTURA VARIABLE DE POLINES POR APOYO EN LA PENDIENTE DE RAMPA, MAYOR DIFICULTAD DE ARMADO POR PENDIENTE, ACARREOS, DESMOLDANTE, DESPERDICIOS, MATERIALES, MANO DE OBRA, HERRAMIENTA Y EQUIPO (P.U.O.T.). | M2 | 1.000000 | $179.40 | $179.40 |
| TOR-208 | SUMINISTRO Y COLOCACION DE ACERO DE REFUERZO FY=4200 KG/CM2, DE 3/8" EN RAMPA DE ESCALERA, INCLUYE: ACARREOS, TRASLAPES, GANCHOS, ALAMBRE DE AMARRE (P.U.O.T.). | TON | 0.025600 | $15,274.07 | $391.02 |
| TOR-208 | SUMINISTRO Y COLOCACION DE ACERO DE REFUERZO FY=4200 KG/CM2, DE 3/8" EN RAMPA DE ESCALERA, INCLUYE: ACARREOS, TRASLAPES, GANCHOS, ALAMBRE DE AMARRE (P.U.O.T.). | TON | 0.025600 | $15,274.07 | $391.02 |
| TOR-290A | SUMINISTRO Y COLOCACION DE CONCRETO F'C = 200 KG/CM2, H.O., INCLUYE: FABRICACION, ACARREO, COLOCACION, NIVELACION, CURADO CON AGUA (P.U.O.T.). | M3 | 0.120000 | $1,649.99 | $198.00 |
| TOR-290A | SUMINISTRO Y COLOCACION DE CONCRETO F'C = 200 KG/CM2, H.O., INCLUYE: FABRICACION, ACARREO, COLOCACION, NIVELACION, CURADO CON AGUA (P.U.O.T.). | M3 | 0.120000 | $1,649.99 | $198.00 |
| Suma de Concepto | | | | $1,536.83 |
| Costo Directo | | | | $1,536.83 |