| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| DOMO | DOMO ACRILICO EN ESCALERAS Y BAÑOS | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Contrato | |||||
| DOMO_SC | Subcontrato de DOMO | M2 | 1.000000 | $1,500.00 | $1,500.00 |
| DOMO_SC | Subcontrato de DOMO | M2 | 1.000000 | $1,500.00 | $1,500.00 |
| DOMO_SC | Subcontrato de DOMO | M2 | 1.000000 | $1,500.00 | $1,500.00 |
| DOMO_SC | Subcontrato de DOMO | M2 | 1.000000 | $1,500.00 | $1,500.00 |
| DOMO_SC | Subcontrato de DOMO | M2 | 1.000000 | $1,500.00 | $1,500.00 |
| DOMO_SC | Subcontrato de DOMO | M2 | 1.000000 | $1,500.00 | $1,500.00 |
| DOMO_SC | Subcontrato de DOMO | M2 | 1.000000 | $1,500.00 | $1,500.00 |
| DOMO_SC | Subcontrato de DOMO | M2 | 1.000000 | $1,500.00 | $1,500.00 |
| Suma de Contrato | $12,000.00 | ||||
| Costo Directo | $12,000.00 |