| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| *TEMP1016 | Guarnición de concreto f'c = 150 pecho de paloma de 20 cm de espesor incluye excavacion y relleno | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 0082-00 | ALAMBRE RECOCIDO NO. 16 | KG | 0.300000 | $15.20 | $4.56 |
| COMBUSTIBLE 03 | GASOLINA | LT | 0.500000 | $7.50 | $3.75 |
| CELOTEX | JUNTA CONSTRUCTIVA DE CELOTEX | M2 | 0.008330 | $97.00 | $0.81 |
| PINTURA P/TRAFICO | CON MICROESFERA | LT | 0.087500 | $90.00 | $7.88 |
| THINER | THINER | LT | 0.050000 | $17.25 | $0.86 |
| ESTOPA | ESTOPA | KG | 0.040000 | $34.50 | $1.38 |
| Suma de Material | $19.24 | ||||
| Mano de Obra | |||||
| CUAD OC 02 | CUAD. 1 OP. DE EQUIPO MENOR. | JOR | 0.166667 | $363.12 | $60.52 |
| Suma de Mano de Obra | $60.52 | ||||
| Auxiliar | |||||
| 03-2170 | CONCRETO HECHO EN OBRA F'C=150 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 1 1/2" | M3 | 0.108580 | $914.32 | $99.28 |
| BAS -CIMMET | CIMBRA METALICA DE 40 CMS DE ALTURA | ml | 0.030130 | $419.25 | $12.63 |
| Suma de Auxiliar | $111.91 | ||||
| Costo Directo | $191.66 |