| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| *TEMP533 | ACABADO PULIDO EN LOSA DE CONCRETO | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGUA | AGUA | M3 | 0.040000 | $46.00 | $1.84 |
| CEMENTO | CEMENTO NORMAL GRIS TIPO I EN SACO | TON | 0.001200 | $1,960.20 | $2.35 |
| CIM1 | MADERA PINO 3a. | pt | 1.100000 | $8.05 | $8.86 |
| Suma de Material | $13.05 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.040000 | $768.76 | $30.75 |
| Suma de Mano de Obra | $30.75 | ||||
| Costo Directo | $43.80 |