| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| *TEMP366 | PINTURA DE ESMALTE ALQUIDALICO COLOR BLANCO SOBRE TUBERIA HIDRAULICA, CON UNA APLICACION PREVIA DE ANTICORROSIVO PRIMARIO DE CROMATO ZINC Y DOS MANOS DE PINTURA, AMBOS MARCA COMEX, INCLUYE: SUMINISTRO DE MATERIALES, ELEVACIÓN Y ACARREO DE LOS MISMOS, MANO DE OBRA, DESPERDICIOS, HERRAMIENTA, EQUIPO Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CROMATO DE ZINC | CROMATO DE ZINC | LT | 0.100000 | $115.06 | $11.51 |
| THINNER | THINNER | LT | 0.166667 | $16.10 | $2.68 |
| BROCHA | BROCHA DE 2 PLG | PZA | 0.100000 | $18.40 | $1.84 |
| ESTOPA | ESTOPA | KG | 0.066667 | $34.50 | $2.30 |
| ANDAMIO-02 | TIJERAS AND. ATLAS | PZA | 0.040000 | $1.07 | $0.04 |
| ESMALTE COMEX 100 | ESMALTE COMEX 100 | LT | 0.200000 | $68.77 | $13.75 |
| Suma de Material | $32.13 | ||||
| Mano de Obra | |||||
| I CUAD PLOMEROS | Cuadrilla plomeros (1 Of. plomero + 1 ayudante) | JOR | 0.020408 | $805.18 | $16.43 |
| Suma de Mano de Obra | $16.43 | ||||
| Costo Directo | $48.56 |