| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| *TEMP1063 | FORJADO DE CANAL PARA RECIBIR REJILLA EN PERIMETRO EXTERIOR DE ALBERCA CON CONCRETO F'C=250 KG/CM2 ARMADO CON VARILLAS DEL NUM. 3 A CADA 20 CM. DE __ x __ CM. INCLUYE: CIBRA, ACERO, COLADO, MATERIALES DE CONSUMO, MANO DE OBRA, HERRAMIENTA Y EQUIPO. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGUA | AGUA | M3 | 0.060000 | $46.00 | $2.76 |
| VARILLA | VARILLA FY=4200 KG/CM2 NO. 3 ( 3/8" ) | KG | 8.000000 | $10.00 | $80.00 |
| ALAMBRE | alambre recocido cal. 18 | KG | 0.350000 | $15.18 | $5.31 |
| CIMBRA PLAY | CIMBRAPLAY 16 MM HOJA DE 1.22 X 2.44 | M2 | 0.200000 | $110.15 | $22.03 |
| CIMEST | madera para estacas | pt | 2.500000 | $8.05 | $20.13 |
| CHAFLAN 1" | CHAFLAN 1" | ML | 2.200000 | $3.20 | $7.04 |
| Suma de Material | $137.27 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.100000 | $768.76 | $76.88 |
| CUAD OC 03 | CUAD. 1 OFICIAL FIERRERO + 1 AYTE | JOR | 0.085000 | $783.18 | $66.57 |
| CUAD OC 08 | CUAD. 8 (1 OF. CARPINTERO O.N. + 1AYTE.) | JOR | 0.200000 | $756.00 | $151.20 |
| Suma de Mano de Obra | $294.65 | ||||
| Equipo | |||||
| AVIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | HR | 0.500000 | $70.42 | $35.21 |
| Suma de Equipo | $35.21 | ||||
| Costo Directo | $467.12 |