| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 5.04 | SUMINISTRO, HABILITADO, COLOCACION Y REMOSION DE CIMBRA EN CIMENTACION CON CIMBRAPLAY, INCLUYE: MATERIALES DE CONSUMO, MANO DE OBRA, HERRAMIENTA Y EQUIPO. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MADERA-6 | CIMBRAPLAY 16 MM HOJA DE 1.22 X 2.44 | M2 | 0.183300 | $105.80 | $19.39 |
| MADERA-6 | CIMBRAPLAY 16 MM HOJA DE 1.22 X 2.44 | M2 | 0.183300 | $105.80 | $19.39 |
| CIMBRAG | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 4.500000 | $7.50 | $33.75 |
| CIMBRAG | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 4.500000 | $7.50 | $33.75 |
| CHAFLAN 1" | CHAFLAN 1" | ML | 1.100000 | $3.20 | $3.52 |
| CHAFLAN 1" | CHAFLAN 1" | ML | 1.100000 | $3.20 | $3.52 |
| CIMBRA-02 | CLAVO | Kg. | 0.150000 | $18.00 | $2.70 |
| CIMBRA-02 | CLAVO | Kg. | 0.150000 | $18.00 | $2.70 |
| COMBUSTIBLE | DIESEL | LT | 0.600000 | $5.98 | $3.59 |
| COMBUSTIBLE | DIESEL | LT | 0.600000 | $5.98 | $3.59 |
| ALAMBRE | alambre recocido cal. 18 | KG | 0.250000 | $15.18 | $3.80 |
| ALAMBRE | alambre recocido cal. 18 | KG | 0.250000 | $15.18 | $3.80 |
| Suma de Material | $133.49 | ||||
| Mano de Obra | |||||
| CUAD OC 08 | CUAD. 8 (1 OF. CARPINTERO O.N. + 1AYTE.) | JOR | 0.130000 | $756.00 | $98.28 |
| CUAD OC 08 | CUAD. 8 (1 OF. CARPINTERO O.N. + 1AYTE.) | JOR | 0.130000 | $756.00 | $98.28 |
| Suma de Mano de Obra | $196.56 | ||||
| Costo Directo | $330.05 |