| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 808 | VALV CHECK COL 125L 38MM | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| VALV CHECK 38 | VALV CHECK COL 125L 38MM mca urrea fig 85t,presion 125 lbs | pza | 1.000000 | $614.00 | $614.00 |
| CINTA TEFLON DE 25 | Cinta teflón de 25 mm | pza | 0.050000 | $21.00 | $1.05 |
| PERMATEX-100 | SELLADOR PARA ROSCAS DE TUBERIAS GALVANIZADAS Y PVC , BOTE DE 100 GRAMOS | PZA | 0.080000 | $75.00 | $6.00 |
| ESTOPA | Estopa | kg | 0.010000 | $19.00 | $0.19 |
| PRENSA/CADENA-R | PRENSA DE CADENA DE 1/8"-41/2" , MODELO CV4 , MARCA REED | PZA | 0.000500 | $1,650.00 | $0.83 |
| Suma de Material | $622.07 | ||||
| Mano de Obra | |||||
| CUADRILLA INST. 01 | Cuadrilla de plomeros ( Plomero + ayudante) | jor | 0.125000 | $1,013.94 | $126.74 |
| Suma de Mano de Obra | $126.74 | ||||
| Costo Directo | $748.81 |