| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| MG106 | YEE DOBLE TAR 100MM | Pza. |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| YEE DOBLE TAR 4X4" | YEE DOBLE TAR 4X4" | PZA | 1.000000 | $159.82 | $159.82 |
| YEE DOBLE TAR 4X4" | YEE DOBLE TAR 4X4" | PZA | 1.000000 | $159.82 | $159.82 |
| Suma de Material | $319.64 | ||||
| Mano de Obra | |||||
| CUADRILLA PLOMEROS | Cuadrilla de Plomeros | jor | 0.076923 | $733.26 | $56.40 |
| CUADRILLA PLOMEROS | Cuadrilla de Plomeros | jor | 0.076923 | $733.26 | $56.40 |
| Suma de Mano de Obra | $112.81 | ||||
| Auxiliar | |||||
| ANDAMIO | MODULO DE 1.55 MTS PARA INSTALACIONES | R/D | 0.083333 | $50.40 | $4.20 |
| ANDAMIO | MODULO DE 1.55 MTS PARA INSTALACIONES | R/D | 0.083333 | $50.40 | $4.20 |
| Suma de Auxiliar | $8.40 | ||||
| Costo Directo | $440.85 |