| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 96 | REUBICACION DE REGISTRO ELECTRICO. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TAPA DE FOFO 84A | TAPA DE FO.FO. 84A | PZA | 1.000000 | $2,638.72 | $2,638.72 |
| MALLA | MALLA ELECTROSOLDADA | M2 | 1.100000 | $21.73 | $23.90 |
| Suma de Material | $2,662.62 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | JOR | 2.500000 | $618.40 | $1,546.00 |
| Suma de Mano de Obra | $1,546.00 | ||||
| Auxiliar | |||||
| EXCAVA-MAN | EXCAVACION POR MEDIO MANUAL EN CEPAS, EN MATERIAL CLASE A, MEDIDO EN BANCO, INCLUYE:MATERIALES MANO DE OBRA Y HERRAMIENTA | M3. | 3.240000 | $131.76 | $426.90 |
| CONCRETO F-C=200 H/O | CONCRETO H.O. F'C=200 KG/CM2, R.N. AGR. MAX. 3/4" | M3 | 0.725760 | $802.68 | $582.55 |
| ACARRE40M | ACARREO HORIZONTAL SIN PENDIENTE. EN CARRETILLA DE 3.5 FT3, A 40.00 M. INCLUYE CARGA Y DESCARGA DEL MATERIAL | M3 | 1.200000 | $41.17 | $49.40 |
| Suma de Auxiliar | $1,058.86 | ||||
| Concepto | |||||
| PLAN-5 | PLANTILLA DE CONCRETO PREMEZCLADO F'C=100 KG/CM2 DE 5 CMS. DE ESPESOR. INCLUYE: MATERIALES, MANO DE OBRA, HERRAMIENTA Y EQUIPO. | M2 | 1.000000 | $63.77 | $63.77 |
| CIMDA | Cimbra en dados,contratrabes y trabes de liga en cimentación, acabado común, incluye: materiales, acarreos, cortes, habilitados, cimbrado descimbrado, mano de obra, equipo y herramienta (P.U.O.T.). | M2 | 7.746400 | $146.08 | $1,131.59 |
| RELL-EXC | RELLENO TENDIDO Y COMPACTADO AL 95% PVSM CON MATERIAL PRODUCTO DE LA EXCAVACION COLOCADO EN CAPAS NO MAYORES DE 20 CMS. DE ESPESOR. | M3 | 2.318400 | $109.33 | $253.47 |
| Suma de Concepto | $1,448.83 | ||||
| Costo Directo | $6,716.32 |