| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 9 | "047-G CONCRETO HIDRAULICO G.11CONCRETO HIDRAULICO, POR UNIDAD DE OBRA TERMINADA (INCISO: 3.01.02.026-H.10): a) SIMPLE, COLADO EN SECO: 2) De F'c=250Kg/cm2 EN SUBESTRUCTURA (EN MURO FRONTAL)" | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO PRE-01 | PREMEZCLADO F`c=250 kg/cm2 | m3 | 1.050000 | $872.00 | $915.60 |
| CONCRETO PRE-02 | BOMBA PARA CONCRETO | M3 | 1.000000 | $110.00 | $110.00 |
| CIMBRA-04 | MADERA DE PINO | PT | 2.500000 | $5.15 | $12.88 |
| CIMBRA-02 | CLAVO | Kg. | 0.020000 | $8.77 | $0.18 |
| Suma de Material | $1,038.65 | ||||
| Mano de Obra | |||||
| CUAD OC 05 | CUAD. 1 ALBAÑIL + 5 PEONES | JOR | 0.030000 | $1,606.57 | $48.20 |
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | JOR | 0.150000 | $618.40 | $92.76 |
| Suma de Mano de Obra | $140.96 | ||||
| Equipo | |||||
| MAQUINARIA-23 | VIBRADOR PARA CONCRETO JOPER 8 HP | HR | 0.200000 | $12.88 | $2.58 |
| Suma de Equipo | $2.58 | ||||
| Auxiliar | |||||
| TRAZO | TRAZO Y NIVELACION | HR | 0.075000 | $50.82 | $3.81 |
| ANDAM | ANDAMIO | DIA | 1.080000 | $25.50 | $27.54 |
| CIMBRA METALICA | CIMBRA METALICA | PZA | 0.005000 | $19,234.27 | $96.17 |
| Suma de Auxiliar | $127.52 | ||||
| Costo Directo | $1,309.71 |