| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 28 | BANQUETA DE 0.53M SOBRE LOSA SEGÚN PROYECTO P.U.O.T. | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO PRE-01 | PREMEZCLADO F`c=250 kg/cm2 | m3 | 0.125000 | $872.00 | $109.00 |
| CONCRETO PRE-02 | BOMBA PARA CONCRETO | M3 | 0.125000 | $110.00 | $13.75 |
| ACERO-01 | ACERO VARIOS DIAMETROS | KG | 13.000000 | $7.00 | $91.00 |
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO | Kg | 0.390000 | $14.00 | $5.46 |
| Suma de Material | $219.21 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | JOR | 0.150000 | $618.40 | $92.76 |
| CUAD OC 62 | CUAD. 1 FIERRERO + 1 AYUDANTE DE FIERRERO | JOR | 0.050000 | $618.40 | $30.92 |
| Suma de Mano de Obra | $123.68 | ||||
| Equipo | |||||
| MAQUINARIA-23 | VIBRADOR PARA CONCRETO JOPER 8 HP | HR | 0.200000 | $12.88 | $2.58 |
| Suma de Equipo | $2.58 | ||||
| Auxiliar | |||||
| TRAZO | TRAZO Y NIVELACION | HR | 0.075000 | $50.82 | $3.81 |
| Suma de Auxiliar | $3.81 | ||||
| Concepto | |||||
| CIMDA | Cimbra en dados,contratrabes y trabes de liga en cimentación, acabado común, incluye: materiales, acarreos, cortes, habilitados, cimbrado descimbrado, mano de obra, equipo y herramienta (P.U.O.T.). | M2 | 0.240000 | $146.08 | $35.06 |
| E.P.02** | TUBO DE CARTON COMPRIMIDO DE 21cm DE DIAMETRO EN CAMELLON | M | 1.000000 | $25.98 | $25.98 |
| Suma de Concepto | $61.04 | ||||
| Costo Directo | $410.32 |