| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 97 | REUBICACION DE REGISTRO PLUVIAL | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| BROCAL Y TAPA | BROCAL Y TAPA | PZA | 1.000000 | $1,500.00 | $1,500.00 |
| ACERO-01 | ACERO VARIOS DIAMETROS | KG | 210.000000 | $7.00 | $1,470.00 |
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO | Kg | 6.300000 | $14.00 | $88.20 |
| Suma de Material | $3,058.20 | ||||
| Mano de Obra | |||||
| CUAD OC 62 | CUAD. 1 FIERRERO + 1 AYUDANTE DE FIERRERO | JOR | 2.500000 | $618.40 | $1,546.00 |
| Suma de Mano de Obra | $1,546.00 | ||||
| Auxiliar | |||||
| CONCRETO F-C=200 H/O | CONCRETO H.O. F'C=200 KG/CM2, R.N. AGR. MAX. 3/4" | M3 | 1.420000 | $802.68 | $1,139.81 |
| ACARRE40M | ACARREO HORIZONTAL SIN PENDIENTE. EN CARRETILLA DE 3.5 FT3, A 40.00 M. INCLUYE CARGA Y DESCARGA DEL MATERIAL | M3 | 6.305000 | $41.17 | $259.58 |
| Suma de Auxiliar | $1,399.38 | ||||
| Concepto | |||||
| 230.1-002 | CIMBRA ACABADO COMUN EN ZAPATAS DE CIMENTACION A BASE DE TRIPLAY DE 3A DE 13 MM, BARROTES, DUELA, POLINES, CHAFLANES, INCLUYE: CIMBRA, DESCIMBRA, DESMOLDANTES, EQUIPO, HERRAMIENTA, MATERIALES, DESPERDICIOS Y MANO DE OBRA | M2 | 18.000000 | $173.33 | $3,119.94 |
| 570.1.002 | PLANTILLA DE 5 CMS. DE ESPESOR DE CONCRETO POBRE F`C=100 KG/CM2 PREMEZCLADO PARA DESPLANTAR CISTERNA, INCLUYE: MATERIALES, DESPERDICIOS, EQUIPO, HERRAMIENTA Y MANO DE OBRA | M2 | 2.890000 | $64.70 | $186.98 |
| DRES-0008. | EXCAVACION A MANO EN MATERIAL TIPO II, EN SECO HASTA 2.00 M., DE PROF. PARA ALOJAR TUBERIA, INCLUYE AFINE DE TALUDES Y ABUNDAMIENTO | M3 | 9.687000 | $82.35 | $797.72 |
| RELL-EXC | RELLENO TENDIDO Y COMPACTADO AL 95% PVSM CON MATERIAL PRODUCTO DE LA EXCAVACION COLOCADO EN CAPAS NO MAYORES DE 20 CMS. DE ESPESOR. | M3 | 10.740000 | $109.33 | $1,174.20 |
| Suma de Concepto | $5,278.85 | ||||
| Costo Directo | $11,282.43 |