| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 29. | REMATE DE GUARNICION Y PARAPETO EN ACCESOS | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACERO-01 | ACERO VARIOS DIAMETROS | KG | 126.010000 | $7.00 | $882.07 |
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO | Kg | 3.780000 | $14.00 | $52.92 |
| Suma de Material | $934.99 | ||||
| Mano de Obra | |||||
| CUAD OC 62 | CUAD. 1 FIERRERO + 1 AYUDANTE DE FIERRERO | JOR | 2.000000 | $618.40 | $1,236.80 |
| Suma de Mano de Obra | $1,236.80 | ||||
| Auxiliar | |||||
| TRAZO | TRAZO Y NIVELACION | HR | 0.075000 | $50.82 | $3.81 |
| CIMBRA APARENTE | CIMBRA APARENTE | M2 | 6.370000 | $126.05 | $802.94 |
| Suma de Auxiliar | $806.75 | ||||
| Concepto | |||||
| 3.02 | CONCRETO HIDRAULICO DE F'C=250 KG/CM2 | m3 | 1.029000 | $1,363.45 | $1,402.99 |
| Suma de Concepto | $1,402.99 | ||||
| Costo Directo | $4,381.53 |