| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 27 | SUMINISTRO Y COLOCACIÓN CADENA DE DESPLANTE 15 X 20 CM | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACER 3-12 | ACERO DE REFUERZO DEL No 3-12 | TON | 0.002280 | $10,000.00 | $22.80 |
| ALAMBRON DE 1/4" | ALAMBRON DE 1/4" | TON | 0.001900 | $11,000.00 | $20.90 |
| ALAMBRE REC#18 | ALAMBRE RECOCIDO CAL 18 | KG | 0.090000 | $17.00 | $1.53 |
| Suma de Material | $45.23 | ||||
| Mano de Obra | |||||
| 03 ALB+PEON | CUADRILLA OFIC ALB+PEON | jor | 0.062500 | $606.94 | $37.93 |
| Suma de Mano de Obra | $37.93 | ||||
| Auxiliar | |||||
| CIMBRA AP CAD CASTI | CIMBRA APARENTE PARA CADENAS Y CASTILLOS | m2 | 0.400000 | $73.20 | $29.28 |
| CONCRETO 150 19MM | CONCRETO F'C=150 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4 HECHO EN OBRA" | M3 | 0.031500 | $679.42 | $21.40 |
| Suma de Auxiliar | $50.68 | ||||
| Costo Directo | $133.85 |