| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 29 | SUMINISTRO Y COLOCACIÓN DE CASTILLOS DE 15 X 15 CM | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACER 3-12 | ACERO DE REFUERZO DEL No 3-12 | TON | 0.002280 | $10,000.00 | $22.80 |
| ALAMBRON DE 1/4" | ALAMBRON DE 1/4" | TON | 0.001600 | $11,000.00 | $17.60 |
| ALAMBRE REC#18 | ALAMBRE RECOCIDO CAL 18 | KG | 0.080000 | $17.00 | $1.36 |
| Suma de Material | $41.76 | ||||
| Mano de Obra | |||||
| 03 ALB+PEON | CUADRILLA OFIC ALB+PEON | jor | 0.076923 | $606.94 | $46.69 |
| Suma de Mano de Obra | $46.69 | ||||
| Auxiliar | |||||
| CIMBRA AP CAD CASTI | CIMBRA APARENTE PARA CADENAS Y CASTILLOS | m2 | 0.300000 | $73.20 | $21.96 |
| CONCRETO 150 19MM | CONCRETO F'C=150 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4 HECHO EN OBRA" | M3 | 0.023600 | $679.42 | $16.03 |
| Suma de Auxiliar | $37.99 | ||||
| Costo Directo | $126.44 |