| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| EST-05 | Concreto premezclado f'c=250kg/cm2 en cimentación para muro perimetral, r.n., tma 20mm. (3/4") rev 14cm, incluye: acarreos a 1a. estacion a 20.00m. | m3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| C1HPR020 | Concreto F'c=250 kg/cm2 normal T.M.A. 20 revenim. 14 grado "A" no bombeable | m3 | 1.000000 | $950.00 | $950.00 |
| ACMXX005 | Agua | m3 | 0.025500 | $86.00 | $2.19 |
| AIGFE052 | Curafest rojo (Fester) | L | 0.000000 | $20.56 | $0.00 |
| HAFAK005 | artesa de concreto | PZA | 0.000000 | $60.00 | $0.00 |
| LABCON01 | muestreos c/cilindro p/lab. | PZA | 0.000000 | $136.74 | $0.00 |
| IMPERMINTEGRAL | IMPERMEABILIZANTE INTEGRAL INCLUIDO EN EL CONCRETO. | M3 | 0.000000 | $80.00 | $0.00 |
| REVENIMIENTO NORMAL | REVENIMIENTO DE CONCRETO 14 Y 18 | M3 | 1.030000 | $90.00 | $92.70 |
| Suma de Material | $1,044.89 | ||||
| Mano de Obra | |||||
| JOGP014 | Cuadrilla de albañiles. Incluye : albañil, ayudante, cabo y herramienta. | jor | 0.400500 | $662.52 | $265.34 |
| Suma de Mano de Obra | $265.34 | ||||
| Equipo | |||||
| EQAVB001 | Vibrador de Concreto mot. gasolina 8 hp Kolher flecha 14" cabezal AA48 de 17/8" (45mm). | h | 0.510000 | $48.30 | $24.63 |
| BOMBA PLUMA | Bomba pluma para concreto con diámetro hasta 4" (102mm) | M3 | 1.030000 | $90.00 | $92.70 |
| Suma de Equipo | $117.33 | ||||
| Costo Directo | $1,427.57 |