| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| PLANTILLA | plantilla de concreto pobre de 100 kg / cm2 | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONC.150 KG/CM2 PREM | tiro directo rev.8-11 | m3 | 0.052500 | $690.00 | $36.23 |
| MADERA-2 | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 0.500000 | $4.60 | $2.30 |
| CLAVO (VARIAS MED.) | CLAVO DE ACERO AL CARBON DE 2" A 4" | KG | 0.020000 | $12.15 | $0.24 |
| ALAMBRE REC | ALAMBRE RECOCIDO CAL. 18 | KG | 0.100000 | $13.00 | $1.30 |
| Suma de Material | $40.07 | ||||
| Mano de Obra | |||||
| CUADRILLA NO.06 | (1 OFICIAL ALBAÑIL + 1 PEON) | JOR | 0.040000 | $628.27 | $25.13 |
| Suma de Mano de Obra | $25.13 | ||||
| Costo Directo | $65.20 |